Aliquot provided phasing plans, design, permit processing, and construction management for this 26-acre retail property. Our team worked with the developer and architect to develop a program of construction phasing and scheduling for the site work, which established the lease commitments to new tenants and assured patron parking and access to stores during construction. Move-in commitments of new major tenants were established with a programmed assurance to minimize disruption to the existing tenants. Selected tasks:
Parking lot rehabilitation plan, rather than reconstruction, which provided ample parking to serve existing stores and timely completion.
Creek reconstruction which required Resource Agency permitting.
Utility relocation and construction were phased incrementally to minimize loss of parking and allow unobstructed access lanes.
Processing through Cal Trans for the widening and construction of frontage improvements on the state highway.
Address extensive shallow ground water throughout the construction area.
Planning for a 350-unit condominium project for the next development phase.